Zhaoqing OFUN Furniture Co., Ltd. Annual production of 100,000 sets of furniture construction projects
Release Time:
2019-05-13
Source:
Environmental Impact Assessment for the first time
According to the"Environmental Impact Assessment Law of the People's Republic of China"and the"Public Participation Measures for Environmental Impact Assessment"(Organization of the Ministry of Ecology and Environment)No.4,etc.,the first public notice of the environmental impact assessment of the project will be carried out in order to understand the public The attitude of the project and the opinions and suggestions on environmental protection are subject to the supervision of the public.Its publicity is as follows:
I.Project Overview
Project Name:Zhaoqing OFUN Furniture Co.,Ltd.has an annual output of 100,000 sets of furniture construction projects;
Construction site:Jintao Avenue,North District of Jintao Industrial Park,Jinli Town,Gaoyao District,Zhaoqing City(next to Zhaoqing Tongsan Glass Technology Co.,Ltd.);
Nature of construction:new construction;
Construction Content:Zhaoqing OFUN Furniture Co.,Ltd.plans to invest 10 million yuan to build a furniture processing project in Jintao Avenue(next to Zhaoqing Tongyue Glass Technology Co.,Ltd.)in Jintao Industrial Park,Jinli Town,Gaoyao District,Zhaoqing City.The total area ofthe project is 34,921 m2,and the total construction area is about 3,1967 m2.The main construction contents are a layer of colloidal screen soft furniture production workshop,one floor office solid wood furniture production workshop,one floor hotel solid wood furniture production workshop,one two-storey warehouse,office living area and water supply,power supply and environmental protection.And other related facilities.After the completion of the project,the production scale will reach 100,000 sets of furniture per year.
Second,the name and contact information of the construction unit
Name of Unit:Zhaoqing OFUN Furniture Co.,Ltd.
Address:Jintao Avenue,North District,Jintao Industrial Park,Jinli Town,Gaoyao District,Zhaoqing City(next to Zhaoqing Tongsan Glass Technology Co.,Ltd.)
Contact:Yang Jiaochun
Contact number:13318882593 13318882593@189.cn
Third,the name and contact information of the environmental impact assessment agency
Name of Unit:Inner Mongolia Tianzhu Environmental Assessment Co.,Ltd.
Certificate No.:National Environmental Assessment,No.1432
Address:No.2#01123,12th Floor,Office Building,Yongye Plaza,Songshan District,Chifeng City,Inner Mongolia Autonomous Region
Contact:Chu Yuanhong
Telephone/fax:16223726662(telephone)
4.Working procedures and main work contents of environmental impact assessment
Evaluation work procedure:
The construction unit entrusts-→formulates the evaluation plan-→data collection and analysis-→environmental monitoring-→preparation of the report-→revision report-→report submission and approval.
Main work content:
Based on the investigation of the environmental status quo within the scope of evaluation,analyze,predict and evaluate the environment that may be caused by the project,and raise the issues that should be paid attention to during the implementation of the project and the environmental protection measures that should be taken to prevent or mitigate the adverse environment of the project to the surrounding environment.influences.
V.Scope and main issues for public consultation
The scope of this public consultation is mainly for the villagers in and around the project and the enterprises and institutions that have direct or indirect relationship with the project;the main items sought are:
1.Suggestions on environmental issues at the location of the construction project and satisfaction with the current environmental quality of the location;
2.Whether the views of the project construction on the social,economic and environmental aspects of the region are acceptable;
3.Any opinions and requirements on the construction unit's pollution prevention measures;
4.Considering from the perspective of social and economic development and environmental protection,whether to support the construction of this project;
5.What opinions and requirements are there for the EIA unit in preparing the EIA report.
6.The main methods and deadlines for public comments
(1)Make oral comments or text messages by telephone(requires detailed address,identity,contact information).
(2)Delivering written comments(representing the address,identity,contact information and signature of the person making the comment,which can be delivered in person or by post,the letter is subject to the postmark date).
Deadline for this feedback:Within 10 working days from the date of announcement.
Zhaoqing OFUN Furniture Co.,Ltd.
May 13,2019